In my blog of the 22 August 2016 I discussed the concept of
feasible development capacity. This concept features in the proposed National Policy
Statement on urban development capacity and the deliberations of the
independent hearings panel that considered the Proposed Auckland Unitary Plan
(PAUP). I questioned the use of the concept to determine zoning envelopes,
especially longer term estimates of required capacity. I acknowledge the need
to consider how much of the theoretical capacity enabled by zonings may be
feasible or realistic, but am unsure if 'commercially feasible development
capacity' is the way to go.
In this blog I want to look at whether the idea of commercially
feasible capacity may help determine what type of zoning should be
applied, if not how much zoning.
The data in Table 1 is from the Auckland independent hearing
panel's report on the recommended PAUP. It shows the total plan enabled
capacity by the four main residential zones used by the PAUP, and the
proportion of that enabled capacity, that was deemed commercially feasible by the council's model.
Table 1: Number of dwellings
Zone
|
Plan enabled capacity
|
Estimated feasible capacity
|
Proportion capacity "feasible"
|
Single House
|
34,445
|
11,259
|
33%
|
Mixed Housing Suburban
|
312,627
|
50,966
|
16%
|
Mixed Housing Urban
|
297,834
|
53,750
|
18%
|
Terrace Housing and Apartment Building
|
325,648
|
45,929
|
14%
|
Total
|
970,554
|
161,904
|
17%
|
So, not much difference in feasibility across the zones.
If we take the land area involved in each of the 4 zones and
the number of dwellings feasible per hectare of land, we start to see the
efficiency of the more intensive zones.
Table 2: Feasible dwellings per ha.
Area (ha)
|
Feasible dwellings per ha
|
|
Single House
|
8,761
|
1.29
|
Mixed Housing Suburban
|
12,497
|
4.08
|
Mixed Housing Urban
|
8,211
|
6.55
|
Terrace Housing and Apartment Building
|
2,384
|
19.27
|
Total
|
31,853
|
5.08
|
The data gives a hint of the issues at play when considering
feasibility and location.
The Single House Zone feasible capacity of 33% is actually
not much different to my estimates done 20 years ago for similar types of zones(as
outlined in my 22 August 2016 blog), albeit by a different methodology. Estimating realistic capacity of zoning that
involves adding a further dwelling to an existing section is not too difficult
to calculate. All you need to know is the number of sections above a minimum
size.
Up to about the end of the 1990s, most development in
Auckland was by way of greenfields expansion and urban infill. The infill bit was mostly adding a further
dwelling to a site, and was often landowner driven, or undertaken by a
development-orientated builder. However, the amount of development realised per
hectare of land is not that great.
Redevelopment is now the most common form of urban
intensification. This is in the sense of existing housing on a section having
to be demolished, removed or shifted to accommodate new housing. This is a more complex process than
infill, requiring more skills and
'deeper pockets'. Suitable sites are
harder to find, with many sites subject to cross-lease or unit title
development. Development timeframes are longer so market ups and downs are more
of a risk. The resulting product may not be affordable , for the developer or the purchaser. It is the type of development undertaken by specialists rather than 'part timers'. Access to finance is critical. These factors are not
taken into account by the feasible development model, and arguably further
reduce what may be 'feasible'.
Stepping away from the Single House Zone, for the other
three zones, feasible capacity drops by close to half, to be in the order of 14
to 18% of total enabled capacity. This reflects the extra 'costs' involved and the finer balance between costs and returns. This
is a fairly tight band of feasibility across the three 'intensive zones'. There is no real
advantage of one zoning type over another in terms of feasibility. So in the
future, could we run off some sort of 15 to 20% figure to determine how much redevelopment capacity
is realistic in the short term?
The number of commercially feasible dwellings per hectare of
land does vary by type of zone. But while the number of feasible dwellings per ha of land
zoned terrace housing and apartments is much higher than the other zones, the
pool of land is much smaller. Arguably, finding development sites will be even harder in this smaller pool.
So do we focus on making the pool of potential development
opportunities as big as possible? This is a pretty simple way of looking at the
issue - just make the whole pie big enough so that hopefully there will be enough
to satisfy everyones needs. Ideally
there would not be a large gap between enabled and feasible capacity. A big gap suggests room for unintended outcomes, especially if
actual development patterns do not match the estimate of feasible development
capacity. Development may end up concentrated in one area, rather than nicely
spread around, and make it hard for infrastructure providers to work out where to put their effort. Equally though, plenty of 'slop' in the system should enable more
room for market forces.
I do think the concept of development feasibility has some
validity in determining where different types of intensity should be
located, and hence plans being able to better correlate enabled capacity with
feasible capacity.
The graph below groups the urban Wards in Auckland into
three rings: Inner, middle and outer. These rings roughly accord with the growth
of the city up to the mid 20th century (inner); post war to about the 1980s
(middle); and last 30 years or so (outer). The feasibility of different house types is
then grouped by these three areas. The data provided is based on the zoning set
out in the recommended version of the PAUP, and so the data is not a picture of
what the market would do, unencumbered by zoning controls.
Also note that the three rings are not of equal size. The
middle ring is by far the largest in terms of the number of existing dwellings.
Not surprisingly in the inner ring of suburbs, it is
apartments that are the most viable type of development, by a long shot. In the outer suburbs,
there is more of a mix. The way that the council's model is structured may mean
that it chooses low rise apartments in these areas, but in reality it is quite
possible that it will be terrace housing, duplexes and town houses that will be
developed.
Figure 1: Feasible
dwelling types by urban location
The heavy lifting in terms of feasible capacity is undertaken by the middle ring suburbs. Not surprising given that in Auckland's case, so much of
the inner ring are heritage areas. But how much capacity needs to be enabled to get to this amount of feasible development?
At the back of all this data is some fairly simple
relationships between land values, construction costs and sale prices. As those
parameters change - particularly as land values rise - then the financials of
development alter and shift towards apartments away from stand alone houses,
even when apartments cost more on a per square metre basis.
This can be seen when feasible capacity is compared to
enabled capacity, in the three rings. Using slightly different data from that
in the figure above (data based on an earlier version of the PAUP), the graph
below shows the existing dwellings (at 2013), the plan enabled capacity and
estimated feasible development.
Figure 2: Dwellings by Urban Location
In the middle ring, only 10% of enable dwellings are
feasible, while in the inner ring, that figure is closer to 30%.
Three things spring to mind in terms of planning principles:
- Does feasible development tend to be scattered development, rather than concentrated development?
- Is density around amenity a better principle that density around transport hubs?
- The urban system is continually adjusting - should zoning also be able to adjust automatically as land values alter?
The first and second questions relate to a long-held planning principle
that clustered intensification around a town centre or along a transport route
is the way to go. There were four main reasons for this. The first relates to
the amenity issues associated with intensification - 'saving the suburbs'. Intensification
should be grouped or concentrated so as to not see existing suburban fabric
substantially modified. The second and third relate to the transport effects of
intensification. The inevitable effect of more people is more traffic - locate
the people close to shops and transport hubs and hopefully that impact is
lessened as rates of walking and cycling and public transport use will be
higher. The extra population close to a centre would also help with sustaining
the viability of that centre. More local services means a more attractive place
to live and less need for travel out of the centre. Finally, infrastructure
providers (particularly Watercare) had a fair idea where infrastructure
upgrades are likely to be needed. All in all, a winning sounding strategy.
But consideration of feasible development has considerably
diluted this strategy. The amount of
development around nodes that is 'feasible' is less than what may have been
hoped for. So to find capacity, either the nodes need to be a lot bigger, or the
suburbs need to be opened up for more growth. The
end result is that in its search of capacity for 30 year time frame, the PAUP
has tended to spread growth across the urban area and while the intensification
enabled by the Terrace Housing and Apartment Buildings zone is important for
capacity, it is no longer the main source of feasible capacity. You could say
that this is the major change between the notified version of the PAUP and the decisions
version: concentrated versus spread
development. This is particularly so for
the middle ring suburbs.
The consideration of commercially feasible capacity also
tends to push consideration of upzoning to areas of higher land values -
coastal areas and inner city areas. If we take the urban Wards and look at
where the highest proportion of enabled dwellings are feasible dwellings, then
the four top Wards are:
Devonport - Takapuna
|
36% of enabled
capacity is feasible
|
Waitemata
|
34%
|
Hibiscus&Bays
|
26%
|
Orakei
|
20%
|
Amenity drives land values, which in turns drives intensification.
But these areas are constrained by a number of factors (not all of which are to
do with the environment), and so to get the capacity figures up, the middle
ring suburbs have had to 'expand' But
the middle ring is the least efficient in terms of turning enabled development
into commercially feasible development.
On the last question - things change, so should zoning - how
can zoning change more easily? 'Fungible' zoning (the ability for zoning to
adjust automatically) is something to look at in more detail in a later blog.